Khammam-Devarapalle (KD-1)


Construction of 4 lane Access Controlled New Greenfield Highway Section of NH-365BG (Khammam-Devarapalle) of length 33.604 km from Thallampadu village to Somavaram village (Design Chainage 0+000 to 33+604) under Inter Corridor Route under Bharatmala Pariyojana on Hybrid Annuity mode in the state of Telangana (Package-I).
State : Telangana
Length : 33.60 KMs
Appointment Date : 31 Dec, 2022
Executed Till Date : 20.90%
Project Cost : INR 772.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Khammam-Devarapalle (KD-2)


Construction of 4 lane Access Controlled New Greenfield Highway Section of NH-365BG (Khammam-Devarapalle) of length 29.513 km from Somavaram village to Chintagudem village (Design Chainage 33+604 to 63+117) under Inter Corridor Route under Bharatmala Pariyojana on Hybrid Annuity mode in the state of Telangana. (Package-II).
State : Telangana
Length : 29.51 KMs
Appointment Date : 13 Sep, 2022
Executed Till Date : 28.10%
Project Cost : INR 637.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Delhi Metro Rail Corporation (Delhi)


Part Design and Construction of Elevated Viaduct and Four Elevated Stations Viz. Keshopur, Paschim Vihar, Peeragarhi and Mangolpuri (Excluding Architectural Finishing Works of Stations, Steel FOB & PEB Works Of Stations) From P2 (excl.) to PP88 (excl.), (Chainage 3118.108 mt. to 6080.447 mt.) and From P103(excl.) to Mangolpuri Station (Incl.) (Chainage 6462.547 Mt to 7012.051 Mt) of Janakpuri West to RK Ashram Corridor (Extn of line 8) of Phase IV Of Delhi MRTS.
State : Delhi
Appointment Date : 23 Jan, 2023
Executed Till Date : 26.60%
Project Cost : INR 412.11 Crores
Commissioned Under : Delhi Metro Rail Corporation (DMRC)


RVNL Bilaspur


Construction of Foundations, Substructure & Super-structure along with River Training/Protection Work, Earthwork & allied works for viaduct 1 & 2 in Between Chainage Km 47+415 to Km 50+900, in connection with Bhanupali-Bilaspur-Beri New Railway Line in District Bilaspur of Himachal Pradesh State, India.
State : Himachal Pradesh
Appointment Date : 24 May, 2023
Executed Till Date : 00.90%
Project Cost : INR 466.11 Crores
Commissioned Under : Rail Vikas Nigam Limited (RVNL)


Neelmangala-Tumkur (Karnataka)


6-Laning with access control from Km 29.435 to Km 74.168 of Neelmangala – Tumkur including Tumkur Bypass Section of NH-48 (old NH-4) in the state of Karnataka under Bharatmala Pariyojana on Engineering, Procurement & Construction (EPC) Mode.
State : Karnataka
Length : 44.73 KMs
Appointment Date : 25 Aug, 2022
Executed Till Date : 15.60%
Project Cost : INR 844.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Karnal Munak Road (Haryana)


Construction of 6-lane Greenfield Karnal Ring Road starting from NH-44 near Village Shamgarh (Design km 0+000 ) and terminating at Karnal – Munak Road (MDR -115) near Village Samalakha (Design km 34+500) under Bharatmala Pariyojana in the state of Haryana on Hybrid Annuity Mode (HAM).
State : Haryana
Length : 34.5 KMs
Appointment Date : 31 Aug, 2023
Executed Till Date : 5.30%
Project Cost : INR 997.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Ganga Expressway (UP)


Engineering, Procurement and Construction Contract for Development of Access Control 6 Lane (Expandable to 8 Lane) Greenfield 'Ganga Expressway' (Group II, From Km 137+600) (Village: Nagla Barah, District: Budaun) to Km. 289+300, (Village:Ubariya Khurd, District: Hardoi), Design Length=151.700 km) in the state of Uttar Pradesh.
State : Uttar Pradesh
Length : 151.7 KMs
Appointment Date : 03 Nov, 2022
Executed Till Date : 29.3%
Project Cost : INR 4970.99 Crores
Commissioned Under : Adani Road Transport Ltd


Raipur-Visakhapatnam OD-5


Development of Six Lane Kaliagura - Baunsaguar Section of NH-130-CD Road from km 249+000 to km 293+000 under Raipur-Visakhapatnam Economic Corridor in the state of Odisha on Hybrid Annuity Mode (Package- OD-5).
State : Odisha
Length : 44 KMs
Appointment Date : 30 May, 2023
Executed Till Date : 47.80%
Project Cost : INR 1492.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Raipur-Visakhapatnam OD-6


Development of Six Lane Baunsaguar-Baraja Section of NH-130-CD Road from Km 293+000 to km 338+500 under Raipur-Visakhapatnam Economic Corridor in the state of Odisha on Hybrid Annunity Mode (Package- OD-6).
State : Odisha
Length : 45.5 KMs
Appointment Date : 01 Jun, 2023
Executed Till Date : 52.50%
Project Cost : INR 1123.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Narnaul Bypass

Construction of proposed Narnaul Bypass (design length 24.0 km) and Ateli Mandi to Narnaul Section of NH-11 from km 43.445 to km 56.900 (Design length 14.0km) as an Economic corridor and Feeder Route Package-2 in the state of Haryana on Hybrid Annuity Mode

State: Haryana

Project Size: Rs. 801.00 Crores (Construction /EPC Cost)

Commissioned under: National Highways Authority of India (NHAI)

Rewari-Ateli Mandi

Upgradation of Four Lane of Rewari-Ateli Mandi section of NH-11 from km 11.780 at Rewari to Ex. Km 43.445 near Ateli Mandi (designed length 30.45 km) as Feeder Route in the state of Haryana on HAM.

State: Haryana

Project Size: Rs. 488.00 Crore (Construction /EPC Cost)

Commissioned under: National Highways Authority of India (NHAI)

Delhi-Vadodara (PKG-4)

Construction of 8-Lane Carriageway starting at Haryana-Rajasthan border and ends at Junction with SH44 (Km 78.800 to Km 115.700) section of Delhi-Vadodara Green Field Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana in Rajasthan.

State: Rajasthan

Project Size: Rs. 997.11 Crore

Commissioned under: National Highways Authority of India (NHAI)

UER PKG-1 (Delhi)


Development of 6-lane Urban Extension Road (UER) – 2 – NH-344 M, Package 1 (from NH 1 to Karala-Kanjhawala road, Km -0+700 to 15+000) in the State of Delhi.
State : Delhi
Length : 14.3 KMs
Appointment Date : 28 Oct, 2021
Executed Till Date : 78.80%
Project Cost : INR 1393.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Raipur-Visakhapatnam AP-01


Development of Six Lane Aluru – Jakkuva Section of NH-130-CD Road from km 365+033 to km 396+800 under Raipur Visakhapatnam Economic Corridor in the state of Andhra Pradesh on Hybrid Annuity Mode [Package- 1 (AP)].
State : Andhra Pradesh
Length : 31.76 KMs
Appointment Date : 31 Mar, 2023
Executed Till Date : 54.60%
Project Cost : INR 1060.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)


Hapur – Moradabad

Six laning of Hapur Bypass to Moradabad Section Including Hapur Bypass from km 50.000 to km 149.867 in the State of Uttar Pradesh on DBFOT (Toll) Basis under NHDP Phase-V. (Total Design Length-79.732 Kms).

State: Uttar Pradesh

Project Size: Rs 972.4 crore

Commissioned under: Modern Road Makers Private Ltd. (A subsidiary of IRB Infrastructure Developers Ltd.)

Nandurbar (Kolde) to Khetia State Highway

Rehabilitation and Up-gradation of Nandurbar (Kolde)- Prakasha-Sahada -Khetia State Highway from existing Km. 50+260 of SH 5, to Km. 99+220 [Design Km. 50+200 to Km. 98+800] to Two lane with paved shoulder/4 lane in the state of Maharashtra.

State: Maharashtra

Date of commencement: 24.07.2017

Project Size: Rs. 298.11 crore

Commissioned under: Maharashtra State Road Development Corporation (MSRDC)

Sunel - (Jhalawar)

Nature of work: Rehabilitation of Raipur- Mundla- Garwara-Dubliya- Karodiya- Sunel- Sirpoi upto Bhawanimandi Boarder.(MDR-214) Km. 0/0 to 20/0

State: Rajasthan

Date of commencement: 28.08.2017

Scheduled date of completion:27.11.2018

Project Size: Rs. 36.29 crore

Commissioned under: Public Works Department,Divn. -Jhalawar,Rajasthan

Sunel - (Jhalawar)

Nature of work: Rehabilitation of a segment of the Raipur-Mundla-Garwara-Dubliya-Karodiya-Sunel-Sirpoi road

State: Rajasthan

Project Size: Rs. 40.26 crore

In Joint Venture with Ranjit Buildcon

Nature of work: Development and construction to four-laning of the Babatpur – Varanasi section of NH-56

State: Uttar Pradesh

Date of commencement: 15/09/2015

Scheduled date of completion: 01/03/2018

Project Size: Rs 126.93 crore (Our Share)/423.11 Cr(Total Cost)

Commissioned under: MORTH

Banar – Kuchera

Development and Upgradation of Banar- Bhopalgarh- Kuchera Highway (SH-63) Km to 126.500 under RSHDP -II (Package No.: WB / RSHDP II/ EPC / 01).

State: Rajasthan

Project Size: Rs. 207.11 crore

Commissioned under: Rajasthan State Highway Development Program - II (RSHDP-II)

Bhawi – Khimsar

Development and Upgradation of Bhawi - Pipar – Khimsar Highway (SH-86C) Length 83.225 Km under RSHDP II (Package No.: WB/RSHDP II/EPC/ 02).

State: Rajasthan

Project Size: Rs. 85.41 crore

Commissioned under: Rajasthan State Highway Development Program - II (RSHDP-II)

Jodhpur – Jojawar

Development & Upgradation of Jodhpur -Marwar Junction -Jojawar Highway (SH-61 & 61A) Length 119.095 Km under RSHDP -II Package No.: WB / RSHDP II/ EPC / 03).

State: Rajasthan

Project Size: Rs. 304.11 crore

Commissioned under: Rajasthan State Highway Development Program - II (RSHDP-II)

Kundal – Jhadol

Upgradation to two lane with paved shoulder from Kundal to Jhadol Section of NH-58E from Ch. 0.000 to 43.90 PKG-01 in the state of Rajasthan on EPC Mode.

State: Rajasthan

Project Size: Rs. 187.11 crore

Commissioned under: Ministry of Road Transportation & Highways, Government of India

Gurgaon – Sohna

Six Laning and Strengthening of new NH-248A from existing km. 11.682 to existing km. 24.400 in the State of Haryana PKG - 2: Existing Ch. Km 24.400 (Design Ch. Km 9.282 to Km 22.000) under NHDP Phase IV on Hybrid Annuity Mode.

State: Haryana

Project Size: Rs. 515.00 Crore (Construction /EPC Cost)

Commissioned under: National Highways Authority of India

Rewari-Bypass

Construction of proposed Rewari Bypass (design length 14.4 Km) as Feeder Route in the state of Haryana on Hybrid Annuity Mode

State: Haryana

Project Cost: Rs. 432.00 Crores (Construction /EPC Cost)

Commissioned under: National Highways Authority of India (NHAI)

Mancherial- Repallewada

Execution of Road Works, Civil 8 Other Associated works on Engineering, Procurement and Construction (EPC) basis for Four laning of NH-363 from Mancherial (Design Km. 0.000/Existing Km. 251.900) to Repallewada (Design Km. 42.000/Existing Km. 288.510) (Design Length = 42.000 Km) in the State of Telangana.

State: Telangana

Project Size: 950 Crore

Commissioned Under: Adani Road Transport Ltd.

Delhi-Vadodara (PKG-8)

Construction of Eight Lane access controlled Expressway starting near start of RoB near Junction with NH-11A to junction with MDR-1 (Baonli-Jhalai road)(Ch. 214.260-247.310) section of Delhi – Vadodara Green field Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana in the State of Rajasthan

State: Rajasthan

Project Cost: Rs. 880.11 Crore

Commissioned under: National Highways Authority of India (NHAI)

Delhi-Vadodara (PKG-9)


Construction of Eight Lane carriageway starting near junction with MDR-1 (Baonli-Jhalai road) to end of interchange on NH-552 (Tonk-Sawaimadhopur) near village Mui (Ch. 247.310 - 292.950) section of Delhi – Vadodara access controlled Green field Alignment (NH-148N) under Bharatmala Pariyojana in the state of Rajasthan.
State : Rajasthan
Length : 45.64 KMs
Appointment Date : 18 Dec, 2020
Executed Till Date : 99.30%
Project Cost : INR 1258.11 Crores
Commissioned Under : National Highways Authority of India (NHAI)